Power Systems Which of the following transmission line is most practically used in load flow analysis? either 1 or 2 nether 1 nor 2 Nominal ∏ Nominal T either 1 or 2 nether 1 nor 2 Nominal ∏ Nominal T ANSWER DOWNLOAD EXAMIANS APP
Power Systems The equation of area control error(ACE) is ACE = ΔPtie +1/ b.Δf ACE = ΔPtie - b.Δf ACE = ΔPtie + b.Δf ACE = ΔPtie - 1/b.Δf ACE = ΔPtie +1/ b.Δf ACE = ΔPtie - b.Δf ACE = ΔPtie + b.Δf ACE = ΔPtie - 1/b.Δf ANSWER DOWNLOAD EXAMIANS APP
Power Systems NTPC (National Thermal Power Cooperation) has its only thermal power generating unit in West Bengal at Bakreshwar. Farakka. Katwa. Durgapur. Bakreshwar. Farakka. Katwa. Durgapur. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Condition for maximum voltage regulation tanφ = X/R cosφ = X/R cosφ = R/X tanφ = R/X tanφ = X/R cosφ = X/R cosφ = R/X tanφ = R/X ANSWER DOWNLOAD EXAMIANS APP
Power Systems Making and breaking currents of 3 phase AC circuit breakers in power system are respectively in what form? RMS and RMS value RMS and Instantaneous value Instantaneous and RMS value any of the above RMS and RMS value RMS and Instantaneous value Instantaneous and RMS value any of the above ANSWER DOWNLOAD EXAMIANS APP
Power Systems A 3 layer and diameter of each strand is d, then find the total diameter of ACSR conductor? d 2d 5d 3d d 2d 5d 3d ANSWER DOWNLOAD EXAMIANS APP