Power Systems Which of following power plants will take long period in erection and installation Thermal. Hydro Power Plant Nuclear. Gas turbine. Thermal. Hydro Power Plant Nuclear. Gas turbine. ANSWER DOWNLOAD EXAMIANS APP
Power Systems For large plants of capacity for more than 15 MW, what type of cooling is used Liquid. Hydrogen. Air. Water. Liquid. Hydrogen. Air. Water. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Inductance of transmission line will decrease when GMD decrease and GMR increase GMD increase and GMR decrease both GMD and GMR increase both GMD and GMR decrease GMD decrease and GMR increase GMD increase and GMR decrease both GMD and GMR increase both GMD and GMR decrease ANSWER DOWNLOAD EXAMIANS APP
Power Systems The pickup value of relay is 6.5 Amp and fault current in relay coil is 39 Amp. Its plug setting multiplier is 7 A. 6 A. 10 A. 8 A. 7 A. 6 A. 10 A. 8 A. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A 3 - Φ, 33 kV oil circuit breaker is rated 1200 A, 2000 MVA, 3 s. The symmetrical breaking current is 1200 A. 35 kA. 104.8 kA. 3600 A. 1200 A. 35 kA. 104.8 kA. 3600 A. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following is/are the stator faults? All of these over current Inter phase faults failure of excitation All of these over current Inter phase faults failure of excitation ANSWER DOWNLOAD EXAMIANS APP