SSC JE Electrical 2019 with solution SET-1
  In a capacitor start single phase induction motor the current in the:

Starting winding lags the voltage
The main winding leads the voltage
Supply lines lead the voltage
Starting winding leads the voltage

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-1
 The meter constant of an energy meter will be given in:

kWh/Revolutions
kW/Revolutions
Revolutions/kWh
Revolutions/kW

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-1
 In an AC network, the load connected is (10 + j10). The phase relation between the voltage applied and the current through the load is:

Voltage and current are in phase with each other
Voltage lags current by 45°
Voltage lags current by 30°
Voltage leads current by 45°

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP