What should be the minimum depth (in metre)of cable trench to dug for laying of 1.1 kV?

 0.90.
 1.05.
  0.75.
 1.20.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A generated station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is

 10 MW
 5 MW
 12 MW
 6 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
For symmetrical network, the neutral current is

 zero
 infinity
 maximum
 any of the above

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
For harnessing low variable water heads, the suitable hydraulic turbine with reaction and adjustable vanes is

 Pelton.
 Francis.
 Impeller.
  Kaplan.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The per unit impedance Z(pu) is given by

 ZΩ* (kVA)b/(KV)²b
 ZΩ* (MVA)b/(KV)²b
 ZΩ* (MVA)b/((KV)²b *100)
 ZΩ* (MVA)b*100/(KV)²b

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
For transmission line which one of the following relation is true?

 AD - BC = 1
 AD - BC = -1
 AD - BC = 0
 AD + BC = 0

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Power Systems

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑