The time taken by the turbine to fall to 0 rpm speed from 3000 rpm is called

  settling time.
  coasting time.
  damping time.
  stopping time.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The power level of nuclear reactor can be increase by ( K = multiplication factor )

  raising the value of K above 1, but later bringing it back to K = 1.
 lowering the value of K below 1 but later bringing it back to K = 1.
 raising the value of K above 1 and keeping it at raised value.
 lowering the value of K below and keeping at that lowered value.