Building Construction The projections of head or sill of a door or window frame are Transoms Chocks Horns Stops Transoms Chocks Horns Stops ANSWER DOWNLOAD EXAMIANS APP
Building Construction Which one of the following activities is not correct as applicable to brick corbels The discontinuous corbels are used to carry heavy concentrated loads The maximum projection of each corbel course should be limited to a quarter brick at a time Stretcher bond is generally used for the construction of brick corbel The maximum projection of the corbel should not be more than the thickness of the wall The discontinuous corbels are used to carry heavy concentrated loads The maximum projection of each corbel course should be limited to a quarter brick at a time Stretcher bond is generally used for the construction of brick corbel The maximum projection of the corbel should not be more than the thickness of the wall ANSWER DOWNLOAD EXAMIANS APP
Building Construction The process of keeping concrete moist for a certain period after its finishing, is known as Finishing of concrete Compaction of concrete Placing of concrete Curing of concrete Finishing of concrete Compaction of concrete Placing of concrete Curing of concrete ANSWER DOWNLOAD EXAMIANS APP
Building Construction If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is 18 12 25 24 18 12 25 24 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed 15 m 20 m 10 m 5 m 15 m 20 m 10 m 5 m ANSWER DOWNLOAD EXAMIANS APP
Building Construction In soft clay of low bearing capacity, the type of steel pile generally used, is Pipe pile H-pile Disc pile Screw pile Pipe pile H-pile Disc pile Screw pile ANSWER DOWNLOAD EXAMIANS APP