The pickup value of relay is 6.5 Amp and fault current in relay coil is 39 Amp. Its plug setting multiplier is

 7 A.
 10 A.
  6 A.
 8 A.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Gas turbine power plants for maximum efficient may have

 Heat exchangers.
  All of above.
 Reheating.
 Multistage compression.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The only place where slip ring induction motors used in thermal power plants is

  lubrication oil pumps.
  none of above.
  coal handling plant.
  conveyors.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The main objectives of electrical power transmission is/are

 Transmission system must be more efficient with minimum line losses
 nether 1 nor 2
 Voltage regulation of the transmission line must be zero or minimum
 both 1 and 2

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
For large plants of capacity for more than 15 MW, what type of cooling is used

  Liquid.
  Water.
  Air.
  Hydrogen.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Maximum power capacity of a transmission line can be increased by

 either 1 or 2
 increasing voltage level
 nether 1 nor 2
 decreasing reactance value

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Power Systems

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑