Process Equipment and Plant Design
The operating velocity in the absorption tower is usually 40-50% of the flooding velocity. Packed absorption towers are normally designed for a pressure drop of about __________ mm of water column per metre height of packing.

100-150
43835
1000-1500
20-40

ANSWER DOWNLOAD EXAMIANS APP

Process Equipment and Plant Design
Weep holes provided in the plates of a distillation column

Facilitate draining out liquid from a tray when the unit is not in operation
Are normally located near the overflow weir so that any delivery of liquid during operation follows approximately the same path as the overflow fluid
Must be large enough (usually 1/4" to 5/8" dia) to prevent plugging but should not deliver excessive amount of fluid during operation
All of these

ANSWER DOWNLOAD EXAMIANS APP