Waste Water Engineering The normal values of over flow rates for sedimentation tanks using coagulant, ranges between 50,000 to 60,000 litres/sqm/day 25,000 to 35,000 litres/sqm/day 40,000 to 50,000 litres/sqm/day 80,000 to 100,000 litres/sqm/day 50,000 to 60,000 litres/sqm/day 25,000 to 35,000 litres/sqm/day 40,000 to 50,000 litres/sqm/day 80,000 to 100,000 litres/sqm/day ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The ratio of maximum sewage flow to average sewage flow for mains up to 1 m in diameter, is 3 1.5 2 4 3 1.5 2 4 ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering In septic tanks, decomposition of organic bacteria, is done by None of these Both types of bacterias Aerobic bacteria Anaerobic bacteria None of these Both types of bacterias Aerobic bacteria Anaerobic bacteria ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering If the peak discharge of a storm water drain (S.W. Drain) is expected to exceed 150 cumecs, the free board to be provided, is 80 cm 100 cm 50 cm 90 cm 80 cm 100 cm 50 cm 90 cm ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The small sewers are cleaned by Flushing Wooden pills Cane rodding None of these Flushing Wooden pills Cane rodding None of these ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering A sewer pipe contains 1 mm sand particles of specific gravity 2.65 and 5 mm organic particles of specific gravity 1.2, the minimum velocity required for removing the sewerage, is 0.45 m/sec 0.35 m/sec 0.40 m/sec 0.30 m/sec 0.45 m/sec 0.35 m/sec 0.40 m/sec 0.30 m/sec ANSWER DOWNLOAD EXAMIANS APP