MGVCL Exam Paper (30-07-2021 Shift 1)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled methid is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix Ybus, n is the total number of buses in the system, m is the number of voltage regulated buses. The size of matrix B' is
∆P/|Vi|= -B' ∆δ
∆Q/|Vi| = -B'' ∆|Vi|

(m-1) x (m-1)
(n-m-1) x (n-m-1)
(n-1) x (n-1)
(n-m) x (n-m)

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Stability of power system can be improved by
1. Reducing voltage of transmission
2. Using parallel transmission lines
3. Using series compensators
Which of the above statements are correct?

1 and 2 only
All 1, 2 and 3
1 and 3 only
2 and 3 only

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
___ is the short time reduction in the rms voltage between 0.1 to 0.9 p.u for a duration of ___

Voltage sag, 0.5 cycle to 1 minute.
Voltage sag, greater than 1 minute
Voltage swell, greater than 1 minute
Voltage swell, 0.5 cycle to 1 minute.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Consider the following statements and choose the correct option:
Statement 1: The magnitude of earth fault current for a given fault position within a winding depends upon the method of neutral grounding.
Statement 2: Earth fault protection for an electric motor is provided by means of instantaneous overcurrent relay.

Both Statement 1 and Statement 2 are TRUE
Statement 1 is FALSE and Statement 2 is TRUE
Both Statement 1 and Statement 2 are FALSE
Statement 1 is TRUE and Statement 2 is FALSE

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP