MGVCL Exam Paper (30-07-2021 Shift 1)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled methid is given below: where B' and B'' are formed using the imaginary part of the bus admittance matrix Ybus, n is the total number of buses in the system, m is the number of voltage regulated buses. The size of matrix B' is ∆P/|Vi|= -B' ∆δ ∆Q/|Vi| = -B'' ∆|Vi|
In FDLF method, B' corresponds to susceptance of unknown of PQ and PV bus Order of B' matrix is = (n -1)*(n - 1) Where n is total no. of buses. Order of B'' = (n - m - 1)*(n - m - 1)
Voltage sag: It is usually associated with system faults but can also be caused by energization of heavy loads or starting of large motors. Voltage sag is the short reduction in the RMS voltage between 0.1 to 0.9 pu for a duration of 0.5 cycle to 1 minute