GETCO Exam Paper (22-07-2015)

GETCO Exam Paper (22-07-2015)
The line current in a three phase unbalanced load are Ir= 4+j6, Ib= 2-j2 and Ic= -3+j2, then zero sequence component of current will be

3 + j6
9 + j10
1 + j2
3 - j6

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Penalty factor in power system economical operation is measure of

Line loss
fuel cost
generation cost
all are correct

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
In a power system network, at which bus the shunt is connected that can be known from

Y bus of the system
reactive power demand
none of these
type of bus

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Shunt capacitors in a substation

consumes lagging VAR
delivers lagging VAR
deliver active power
consume active power

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Calculate torque developed by the 3-phase, 5 HP, 4 pole induction motor runs at 1500 rpm

22 N-m
10 N-m
0 N-m
23.5 N-m

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

P = 2πTN/60 where N is speed in rpm

GETCO Exam Paper (22-07-2015)
When the load is suddenly increased in the receiving end of the system, the phase shift will

Not affected
remains same
decrease
increase

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON GETCO Exam Paper (22-07-2015)

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑