GETCO Exam Paper (22-07-2015) The line current in a three phase unbalanced load are Ir= 4+j6, Ib= 2-j2 and Ic= -3+j2, then zero sequence component of current will be 3 - j6 1 + j2 3 + j6 9 + j10 3 - j6 1 + j2 3 + j6 9 + j10 ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which power plant may take several days to start up and shunt down? Base load solar power plant none of these Peak load Base load solar power plant none of these Peak load ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The magnitude of sum of two sinusoidal AC voltages is equal to the magnitude of each individual voltage, What must be the phase difference between voltages? 180 90 60 120 180 90 60 120 ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The area under the load duration curve represents Maximum demand of the power station average load of the system base load of the system energy generated in the period considered Maximum demand of the power station average load of the system base load of the system energy generated in the period considered ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In a power system network, at which bus the shunt is connected that can be known from reactive power demand none of these Y bus of the system type of bus reactive power demand none of these Y bus of the system type of bus ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) For selecting low voltage cable which of the following factors is not important? short circuit current rating voltage grade permissible voltage drop current carrying capacity short circuit current rating voltage grade permissible voltage drop current carrying capacity ANSWER DOWNLOAD EXAMIANS APP