Building Construction The foundation in which a cantilever beam is provided to join two footings, is known as Strip footing Raft footing Combined footing Strap footing Strip footing Raft footing Combined footing Strap footing ANSWER DOWNLOAD EXAMIANS APP
Building Construction In case of Raymond pile Diameter of top of piles varies from 40 cm to 60 cm Diameter of pile at bottom varies from 20 cm to 28 cm Lengths vary from 6 m to 12 m All listed here Diameter of top of piles varies from 40 cm to 60 cm Diameter of pile at bottom varies from 20 cm to 28 cm Lengths vary from 6 m to 12 m All listed here ANSWER DOWNLOAD EXAMIANS APP
Building Construction Dampness causes Crumbling of plaster Growth of termites Bleaching of paints Efflorescence Crumbling of plaster Growth of termites Bleaching of paints Efflorescence ANSWER DOWNLOAD EXAMIANS APP
Building Construction If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is 12 24 18 25 12 24 18 25 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The wedge shaped bricks forming an arch ring, are called Soffits Voussoirs Haunches Spandrils Soffits Voussoirs Haunches Spandrils ANSWER DOWNLOAD EXAMIANS APP
Building Construction The minimum distance between the centers of bulb of diameter du, of a multi under reamed piles, is 1.5 du 1.25 du 1.35 du 1.75 du 1.5 du 1.25 du 1.35 du 1.75 du ANSWER DOWNLOAD EXAMIANS APP