Building Construction The foundation in which a cantilever beam is provided to join two footings, is known as Raft footing Strap footing Combined footing Strip footing Raft footing Strap footing Combined footing Strip footing ANSWER DOWNLOAD EXAMIANS APP
Building Construction For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is 5, 4, 3, 2, 1 2, 1, 3, 5, 4 3, 2, 5, 1, 4 1, 2, 3, 4, 5 5, 4, 3, 2, 1 2, 1, 3, 5, 4 3, 2, 5, 1, 4 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The raft slab is projected beyond the outer walls of the structure by 5 to 10 cm 15 to 20 cm 25 to 30 cm 30 to 45 cm 5 to 10 cm 15 to 20 cm 25 to 30 cm 30 to 45 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Pile foundation is generally provided if soil is Compressible All listed here Made up Water logged Compressible All listed here Made up Water logged ANSWER DOWNLOAD EXAMIANS APP
Building Construction In the construction of arches, sand box method is used for Centring Striking of centring None of these Actual laying of arch work Centring Striking of centring None of these Actual laying of arch work ANSWER DOWNLOAD EXAMIANS APP
Building Construction The angle between skew back of a flat arch and the horizontal, is kept approximately equal to 60° 90° 30° 0° 60° 90° 30° 0° ANSWER DOWNLOAD EXAMIANS APP