Waste Water Engineering The formula V = (1/n) r2/3 Kutter’s formula Bazin’s formula Chezy’s formula Manning’s formula Kutter’s formula Bazin’s formula Chezy’s formula Manning’s formula ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering At the junction of sewers Top of smaller sewer is kept lower Top of larger sewer is kept lower None of these Tops of both the sewers are at the same level Top of smaller sewer is kept lower Top of larger sewer is kept lower None of these Tops of both the sewers are at the same level ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering ¾th or ¼th extra space is left in sewer pipes at maximum discharge for Unexpected increase in population Large scale infiltration of storm water Low estimates of the average and maximum flows All listed here Unexpected increase in population Large scale infiltration of storm water Low estimates of the average and maximum flows All listed here ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering In sewers designed with self cleansing velocity, Neither silting nor scouring occurs at the bottom The bottom is silted Both silting and scouring occur at the bottom The bottom is scoured Neither silting nor scouring occurs at the bottom The bottom is silted Both silting and scouring occur at the bottom The bottom is scoured ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering In sewers the velocity of flow should not be Less than 10 m/sec Less than the self-cleansing velocity More than the self-cleansing velocity More than 20 m/sec Less than 10 m/sec Less than the self-cleansing velocity More than the self-cleansing velocity More than 20 m/sec ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The density of population over 40 hectares is 250/hectare. If water supply demand per day is 200 litres and sewage discharge is 80% of water supply, the sewage flow in sewers of separate system, is 0.05556 cumec 0.0556 cumec 0.05552 cumec 0.05554 cumec 0.05556 cumec 0.0556 cumec 0.05552 cumec 0.05554 cumec ANSWER DOWNLOAD EXAMIANS APP