GETCO Exam Paper (22-07-2015) The area under the load duration curve represents Maximum demand of the power station energy generated in the period considered base load of the system average load of the system Maximum demand of the power station energy generated in the period considered base load of the system average load of the system ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Steady state stability of a power system is improved by reducing fault clearing time decreasing generator inertia using double circuit line instead of single circuit line by fast switching reducing fault clearing time decreasing generator inertia using double circuit line instead of single circuit line by fast switching ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Penalty factor in power system economical operation is measure of Line loss generation cost fuel cost all are correct Line loss generation cost fuel cost all are correct ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The line current in a three phase unbalanced load are Ir= 4+j6, Ib= 2-j2 and Ic= -3+j2, then zero sequence component of current will be 9 + j10 3 + j6 3 - j6 1 + j2 9 + j10 3 + j6 3 - j6 1 + j2 ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) For formation of the Y bus matrix (using node voltage analysis) in power system network modelling _____ is used KVL Faraday's law KCL all are correct KVL Faraday's law KCL all are correct ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which of the following is the wrong statement in terms of slack bus? it should be the largest generator bus in the system it should be located at the centre of the area it has finite reactive power generation capability voltage and angle is specified at this bus it should be the largest generator bus in the system it should be located at the centre of the area it has finite reactive power generation capability voltage and angle is specified at this bus ANSWER DOWNLOAD EXAMIANS APP