GETCO Exam Paper (22-07-2015) Shunt compensation in EHV line is resorted to Improve the stability Improve voltage profile Increase line impedance Reduce the fault level Improve the stability Improve voltage profile Increase line impedance Reduce the fault level ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Who is the 2012 London Olympics bronze medalist in badminton? Saina Sania Jwala Gutta Ashwini Ponnappa Saina Sania Jwala Gutta Ashwini Ponnappa ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Two watt meter method for 3 phase circuit is preferred over other methods because it can be used for balanced or unbalanced load PF of the load can also be estimated all are correct it can be used for star or delta connected load it can be used for balanced or unbalanced load PF of the load can also be estimated all are correct it can be used for star or delta connected load ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) A transformer has negative voltage regulation when its load PF is unity lagging zero leading unity lagging zero leading ANSWER EXPLANATION DOWNLOAD EXAMIANS APP Voltage regulation = ((no load voltage)-(full load voltage)/(no load voltage))VR at leading PF = ((I*R*cosφ)-(I*X*sinφ))/VVR at lagging PF = ((I*R*cosφ)+(I*X*sinφ))/V
GETCO Exam Paper (22-07-2015) Fast excitation system of the generator will _____ Improve the power factor Improve the voltage control Improve the dynamic stability Improve the reactive power control Improve the power factor Improve the voltage control Improve the dynamic stability Improve the reactive power control ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In sub stations for making and breaking of load current relays are used load interrupter switches are used circuit breakers are used isolators are used relays are used load interrupter switches are used circuit breakers are used isolators are used ANSWER DOWNLOAD EXAMIANS APP