GETCO Exam Paper (22-07-2015) Shunt compensation in EHV line is resorted to Improve voltage profile Reduce the fault level Increase line impedance Improve the stability Improve voltage profile Reduce the fault level Increase line impedance Improve the stability ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) When the load is suddenly increased in the receiving end of the system, the phase shift will decrease Not affected increase remains same decrease Not affected increase remains same ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The relay which is most sensitive to power swings (mal operation) is Mho Relay Impedance Relay Over current Relay Reactance Relay Mho Relay Impedance Relay Over current Relay Reactance Relay ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In a power system network, at which bus the shunt is connected that can be known from reactive power demand Y bus of the system none of these type of bus reactive power demand Y bus of the system none of these type of bus ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which of the following is the most likely reason for large overshoot in a control system? presence of dead time delay high retarding torque High gain in a system high positive correcting torque presence of dead time delay high retarding torque High gain in a system high positive correcting torque ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which of the following breaking method save energy? regenerative breaking dynamic breaking plugging resistor breaking regenerative breaking dynamic breaking plugging resistor breaking ANSWER EXPLANATION DOWNLOAD EXAMIANS APP three types of electric breaking:Regenerative breaking( leads to economic and energy consevation)pugging (more efficient method of breaking)rheostatic breaking