Industrial Engineering and Production Management Scheduling Determines the programme for the operations Is concerned with starting of processes Regulates the progress of job through various processes Prescribes the sequence of operations to be followed Determines the programme for the operations Is concerned with starting of processes Regulates the progress of job through various processes Prescribes the sequence of operations to be followed ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.84 0.5 0.95 0.66 0.84 0.5 0.95 0.66 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Activity slack or float of any event on a PERT/CPM chart is represented by Latest start time of the event earliest start time of the event Anyone of the above Latest finish time of event earliest finish time of the event Latest start time of succeeding event earliest finish time of preceding event activity time Latest start time of the event earliest start time of the event Anyone of the above Latest finish time of event earliest finish time of the event Latest start time of succeeding event earliest finish time of preceding event activity time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Work study comprises following main techniques Time study and work measurement Method study and time study Method study and work measurement Method study and job evaluation Time study and work measurement Method study and time study Method study and work measurement Method study and job evaluation ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Military organisation is known as All of these Line and staff organisation Functional organisation Line organisation All of these Line and staff organisation Functional organisation Line organisation ANSWER DOWNLOAD EXAMIANS APP