Industrial Engineering and Production Management
When slack of an activity is negative

It represents that a programme falls behind schedule and additional resources are required to complete the project in time
All of these
It represents a situation where extra resources are available and the completion of project is not delayed
The activity is critical and any delay in its performance will delay the completion of whole project

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Pick up the incorrect statement from the following. A critical ratio scheduling

All of the these
Adjusts automatically changes in activity progress
Establishes the relative priorities among various activities on a common basis
Determines the status of each activity

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Dispatching

Is concerned with the starting of processes
Regulates the progress of job through various processes
Prescribes the sequence of operations to be followed
Determines the programme for the operations

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Time study is carried out

By observing and recording the time taken by the operator for an operation
By finding all the significant informations regarding the job, work place and machine tool etc
All of these
By breaking up each operation into small elements which are measurable with the help of the measuring device accurately

ANSWER DOWNLOAD EXAMIANS APP