The essential condition for the decompression of an activity is that

After decompression the time of an activity invariably exceeds its normal time
The project time should change due to decompression
An activity could be decompressed to the maximum extent of its normal time
An activity could be decompressed to the maximum extent of its normal time

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
In order that linear programming techniques provide valid results

Relations between factors must be linear (negative)
Relations between factors must be linear (positive)
Either (A) or (B)
Only one factor should change at a time, others remaining constant

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
The correct sequence of phases in value engineering is

Information phase, creative phase, investigation phase, evaluation phase
Creative phase, investigation phase, evaluation phase, information phase
Investigation phase, information phase, creative phase, evaluation phase
Creative phase, information phase, investigation phase, evaluation phase