GETCO Exam Paper (30-11-2008) The symmetrical components are used in fault analysis because the number of equations become lesser the sequence networks do not have mutual couplings none of these the result are in terms of symmetrical components the number of equations become lesser the sequence networks do not have mutual couplings none of these the result are in terms of symmetrical components ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) If the +Ve, -Ve & zero sequence reactances of an elements of a power system are 0.3, 0.3 & 0.8 p.u. respectively, the element would be synchronous motor static load synchronous generator transmission line synchronous motor static load synchronous generator transmission line ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) A material best suited for manufacturing of fuse wire is silver zinc aluminium copper silver zinc aluminium copper ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Rewirable fuse has _____ time-current characteristic inverse linear square none of these inverse linear square none of these ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The delay fuses are used for protection of none of these motors fluorescent lamp light circuits none of these motors fluorescent lamp light circuits ANSWER DOWNLOAD EXAMIANS APP