GETCO Exam Paper (30-11-2008) If the +Ve, -Ve & zero sequence reactances of an elements of a power system are 0.3, 0.3 & 0.8 p.u. respectively, the element would be static load synchronous generator transmission line synchronous motor static load synchronous generator transmission line synchronous motor ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) If a combination of HRC fuse and a C.B. is employed, the C.B. operates for short circuit currents low over load currents this combination is never employed in practice under all abnormal currents short circuit currents low over load currents this combination is never employed in practice under all abnormal currents ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The Non-co-operation movement was launched by Mahatma Gandhi in 1926 1921 1920 1905 1926 1921 1920 1905 ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) When transformers or switchgears are to be installed in a transmission line, the poles used are J type H type L type I type J type H type L type I type ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The delay fuses are used for protection of none of these light circuits fluorescent lamp motors none of these light circuits fluorescent lamp motors ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Burden of the relay is _____ rating of relay voltage watt volt-amp. current voltage watt volt-amp. current ANSWER DOWNLOAD EXAMIANS APP