GETCO Exam Paper (30-11-2008) A material best suited for manufacturing of fuse wire is aluminium zinc copper silver aluminium zinc copper silver ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) In a dry type transformer, accumulation of dust on the windings and core is likely to cause short circuiting of secondary winding reduction in heat dissipation corrosion of core material short circuiting of primary winding short circuiting of secondary winding reduction in heat dissipation corrosion of core material short circuiting of primary winding ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The power handling capabilities of transmission lines are both (a) & (c ) determined by system operators set by design factors controlled by load frequency control equipments both (a) & (c ) determined by system operators set by design factors controlled by load frequency control equipments ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) In the parallel operation of transformers, which statement is false transformers kVA ratings equal None of these transformers transformation ratios same transformers voltage ratings same transformers kVA ratings equal None of these transformers transformation ratios same transformers voltage ratings same ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Transfer of power between two power systems takes place with power flowing from the system with the Lagging power angle Higher input current Greater leading power angle Higher voltage level Lagging power angle Higher input current Greater leading power angle Higher voltage level ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) If a power system is transiently stable, it will oscillate beyond the first swing is always dynamically stable both (a) & (c ) may be dynamically unstable will oscillate beyond the first swing is always dynamically stable both (a) & (c ) may be dynamically unstable ANSWER DOWNLOAD EXAMIANS APP