Industrial Engineering and Production Management PMTP (predetermined motion time systems) include WFS (work factor systems) All of these MTM (method time measurement) BNTS (basic motion time study) WFS (work factor systems) All of these MTM (method time measurement) BNTS (basic motion time study) ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following is independent of sales forecast? Inventory control Productivity Production control Production planning Inventory control Productivity Production control Production planning ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A diagram showing the path followed by men and materials while performing a task is known as Flow diagram Travel chart String diagram Flow process chart Flow diagram Travel chart String diagram Flow process chart ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.66 0.84 0.5 0.95 0.66 0.84 0.5 0.95 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Critical path on PERT/CPM chart is obtained by joining the events having Average slack No slack Maximum slack Minimum slack Average slack No slack Maximum slack Minimum slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The most popular type of organisation used for Civil Engineering Constructions is Line organization Effective organization Line and staff organization Functional organization Line organization Effective organization Line and staff organization Functional organization ANSWER DOWNLOAD EXAMIANS APP