Industrial Engineering and Production Management
PERT stands for

Program Estimation and Reporting Technique
Planning Estimation and Resulting Technique
Program Evaluation and Review Technique
Process Estimation and Review Technique

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Pick up the incorrect statement from the following. A critical ratio scheduling

Adjusts automatically changes in activity progress
All of the these
Establishes the relative priorities among various activities on a common basis
Determines the status of each activity

ANSWER DOWNLOAD EXAMIANS APP