MGVCL Exam Paper (30-07-2021 Shift 1)
Murray loop test is performed on a faulty cable 300 m long. At balance, the resistance connected to the faulty core was set at 15 Ω and the resistance of the resistor connected to the sound core was 45 Ω. Calculate the distance of the fault point from the test end.