The magnitude of the generator earth-fault current is limited by

inserting the stabilizing resistance in series with the relay
using higher rating CTs
controlling field exciter
inserting suitable resistance in neutral grounding circuit

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a short circuit test on circuit breaker, time to reach the peak re-striking voltage is 50 µs with the peak restriking voltage of 100 kV. Determine average RRRV (Rate of rise re-striking voltage)?

4 x 10⁶ kV/sec
2 x 10⁶ kV/sec
1 x 10⁶ kV/sec
3 x 10⁶ kV/sec

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A single phase motor connected to 415 V, 50 Hz supply takes 30 A at a power factor of 0.7 lagging. Calculate the capacitance required in parallel with the motor to raise the power factor to 0.9 lagging.

96.32 µF
66.32 µF
76.32 µF
86.32 µF