MGVCL Exam Paper (30-07-2021 Shift 2)
If no load is connected to solar PV system,

it will start reflecting the light
its voltage will go on increasing till its breakdown
it will stop absorbing light
it will dissipate energy in the panel and increase its temperature

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A three-phase, 12 kV, 50 Hz and 300 kW load is operating at 0.8 pf lag. If the pf is to be improved to unity, using star connected capacitor, the per phase value of the reactive VAR required is:

75 kVAR
25 kVAR
50 kVAR
100 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP