Waste Water Engineering It is customary to design a sewer for D.W.F. on the basis of Average demand Four times the average demand Twice the average demand Thrice the average demand Average demand Four times the average demand Twice the average demand Thrice the average demand ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The normal value of over flow rates for plain primary sedimentation tanks, ranges between 40,000 to 50,000 litres/sqm/day 80,000 to 100,000 litres/sqm/day 25,000 to 35,000 litres/sqm/day 50,000 to 60,000 litres/sqm/day 40,000 to 50,000 litres/sqm/day 80,000 to 100,000 litres/sqm/day 25,000 to 35,000 litres/sqm/day 50,000 to 60,000 litres/sqm/day ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The minimum recommended diameter of sewers, is 20 cm 5 cm 15 cm 10 cm 20 cm 5 cm 15 cm 10 cm ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Oxidation process results in the formation of All of these Nitrates Carbon dioxide Sulphates All of these Nitrates Carbon dioxide Sulphates ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The non-clog pump which permits solid matter to pass out with the liquid sewage, is Centrifugal pump None of these Reciprocating pump Pneumatic ejector Centrifugal pump None of these Reciprocating pump Pneumatic ejector ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering If the depletion of oxygen is found to be 5 ppm after incubating a 2.5% solution of sewage sample for 5 days at 21°C, B.O.D. of the sewage is 150 ppm 200 ppm 100 ppm 50 ppm 150 ppm 200 ppm 100 ppm 50 ppm ANSWER DOWNLOAD EXAMIANS APP