MGVCL Exam Paper (30-07-2021 Shift 3)
In two-part tariff, the ____ charges depend upon the maximum demand of the consumer and the ____ charges depend upon the number of units consumed by the consumer.

semi-fixed, running
fixed, semi-fixed
fixed, running
running, fixed

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
The sites where the capacity factor is ____ are not considered suitable for wind power generation.

less than 12%
greater than 24%
greater than 12%
less than 24%

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
The DC offset in fault current causes conventional over-current (OC) relays to :

under-reach
reach remains unaffected due to DC offset
sometimes under-reach and sometimes over-reach
over-reach

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Which of the following statements are correct?
(i) Advanced metering infrastructure (AMI) is typically more automated and allows real- time, on-demand interrogations with metering endpoints.
(ii) An Automated Meter Reading (AMR) device only communicates from the customer to the energy supplier.
(iii) AMR meters only provide kWh information and possible peak kW demand for the month.

(i) and (iii) only
(ii) and (iii) only
(i) and (ii) only
(i), (ii) and (iii)

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP