Power Systems In thermal plant most of the energy is wasted in boiler condenser turbines ESP boiler condenser turbines ESP ANSWER DOWNLOAD EXAMIANS APP
Power Systems In an induction relay for a particular current setting the operating time 4 sec. When the time multiplier setting is 0.8 if the time multiplier setting is rest to 1 the operating time is 5. 1. un changed. 10. 5. 1. un changed. 10. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In a pressurized water reactor both B and C. heavy water is used as both coolant and moderator. water is used at high pressure so that it is available is liquid from at about 280° C. the coolant water boils in the reactor core. both B and C. heavy water is used as both coolant and moderator. water is used at high pressure so that it is available is liquid from at about 280° C. the coolant water boils in the reactor core. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Peak load power plants is/are diesel plant pumped storage plant both 1 and 2 nuclear plants diesel plant pumped storage plant both 1 and 2 nuclear plants ANSWER DOWNLOAD EXAMIANS APP
Power Systems In a 400 KV network, 360 KV is recorded at a 400 KV bus. The reactive power absorbed by shunt rated for 50 MVAr, 400 KV connected at the bus is 45 MVAr. 61.73 MVAr. 55.56 MVAr. 40.5 MVAr. 45 MVAr. 61.73 MVAr. 55.56 MVAr. 40.5 MVAr. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Reflector of a nuclear reactor are made up of steel. cast iron. boron. beryllium. steel. cast iron. boron. beryllium. ANSWER DOWNLOAD EXAMIANS APP