Industrial Engineering and Production Management In steel plant the most important system for materials handling is Cranes and hoists Locos Trucks Conveyors Cranes and hoists Locos Trucks Conveyors ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is 25 100 50 75 25 100 50 75 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Gantt charts provide information about Material handling layout Production schedule Determining selling price Break-even point analysis Material handling layout Production schedule Determining selling price Break-even point analysis ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The unit cost in case of batch production is __________as compared to jobbing production. Low High None of these Same Low High None of these Same ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT requires Double time estimate Single time estimate Triple time estimate None of the listed here Double time estimate Single time estimate Triple time estimate None of the listed here ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Earliest finish time can be regarded as Latest finish time duration of activity Earliest start time + duration of activity Earliest start time duration of activity Latest finish time + duration of activity Latest finish time duration of activity Earliest start time + duration of activity Earliest start time duration of activity Latest finish time + duration of activity ANSWER DOWNLOAD EXAMIANS APP