Process Equipment and Plant Design In packed absorption tower, onset of flooding usually occurs at a pressure drop of about __________ mm of water column per metre height of packing. 200-250 750-1000 50-75 25-50 200-250 750-1000 50-75 25-50 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The force due to wind load acting on a tall vessel depends upon its All of these Outside diameter Shape Height All of these Outside diameter Shape Height ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design With increase in temperature drop (in a shell and tube heat exchanger), the LMTD correction factor, FT Increases linearly Remains constant Increases very rapidly Decreases very rapidly Increases linearly Remains constant Increases very rapidly Decreases very rapidly ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In case of bubble cap distillation column of diameter greater than 1.2 metres, the cap diameter is roughly about __________ cms. 10 35 30 20 10 35 30 20 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Wind load consideration in the design of a support can be neglected, when the vessel is Short (< 2 m) and housed indoor Tall (say 30 metres), but is full of liquid Tall but empty None of these Short (< 2 m) and housed indoor Tall (say 30 metres), but is full of liquid Tall but empty None of these ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In shell and tube heat exchangers, straight tie rods are used to Hold baffle in space None of these Account for thermal strain Fix the tubes in position Hold baffle in space None of these Account for thermal strain Fix the tubes in position ANSWER DOWNLOAD EXAMIANS APP