Process Equipment and Plant Design In packed absorption tower, onset of flooding usually occurs at a pressure drop of about __________ mm of water column per metre height of packing. 50-75 200-250 25-50 750-1000 50-75 200-250 25-50 750-1000 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In the case of a shell and tube heat exchanger, the logarithmic mean temperature difference Is always less than arithmetic mean value, but more than geometric mean value Is always more than arithmetic mean value and the geometric mean value Is always less than arithmetic average value May be either more or less than geometric mean and arithmetic mean value depending upon whether the flow of stream is co-current or counter-current Is always less than arithmetic mean value, but more than geometric mean value Is always more than arithmetic mean value and the geometric mean value Is always less than arithmetic average value May be either more or less than geometric mean and arithmetic mean value depending upon whether the flow of stream is co-current or counter-current ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Safety valves are provided in chemical equipments to guard against excessive Pressure/pressure fluctuation Temperature Noise Turbulence Pressure/pressure fluctuation Temperature Noise Turbulence ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Tubes are fixed to the tube sheet (a thick circular metallic plate) by the method of tube rolling and brazing (non-removable) or ferrule connection (removable). Thickness of the tube, sheet is normally __________ the outside diameter of the tube but in no case it should be less than 22 mm (7/8"). Half Equal to Three fourth 1.5 times Half Equal to Three fourth 1.5 times ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Number of evaporators which can be used in service in a multiple effect evaporation system is limited by the Economic limit reached, when the plant cost exceeds the saving of steam Neither A nor B Practical limit reached, due to low heat transfer rate because of inadequate temperature difference Both A & B Economic limit reached, when the plant cost exceeds the saving of steam Neither A nor B Practical limit reached, due to low heat transfer rate because of inadequate temperature difference Both A & B ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In a multipass shell and tube heat exchanger, the problem of differential expansion between the shell and tube passes is taken care of by using a Either A or B U-bend Floating head tube sheet Neither A nor B Either A or B U-bend Floating head tube sheet Neither A nor B ANSWER DOWNLOAD EXAMIANS APP