GETCO Exam Paper (22-07-2015)

GETCO Exam Paper (22-07-2015)
In a power system network, at which bus the shunt is connected that can be known from

type of bus
Y bus of the system
reactive power demand
none of these

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Who is the 2012 London Olympics bronze medalist in badminton?

Saina
Jwala Gutta
Sania
Ashwini Ponnappa

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Speed of induction motor at rated torque is _____ than at maximum torque.

same
greater
lesser
depends on load

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Which power plant may take several days to start up and shunt down?

none of these
Base load
Peak load
solar power plant

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
The value of holding ratio of relay is always

zero
greater than 1
less than 1
Infinite

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
The surge impedance loading of the line will _____ if the length of the line is double

four times
remains same
become half
double

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

Surge impedance is independent of length of the line

MORE MCQ ON GETCO Exam Paper (22-07-2015)

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑