Docks and Harbor Engineering If H is the height of the wave expected, then the height of the breakwater is generally taken as 1.2 H to 1.25 H above the datum 1.2 H to 1.25 H above the low water level 1.2 H to 1.25 H above the high water level 1.2 H to 1.25 H above the mean sea level 1.2 H to 1.25 H above the datum 1.2 H to 1.25 H above the low water level 1.2 H to 1.25 H above the high water level 1.2 H to 1.25 H above the mean sea level ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Assertion A : Marine structures are made specially bulky and strong.Reason R : Sea insects result in undermining of the hardest and the soundest building material.Select your answer based on the coding system given below: A is false but R is true. Both A and R are true but R is not the correct explanation of A is true but R is false. Both A and R are true and R is the correct explanation of A is false but R is true. Both A and R are true but R is not the correct explanation of A is true but R is false. Both A and R are true and R is the correct explanation of ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Minimum width of ship clearance shall be (where “B” is beam of the design vessel) 50 m B or 30 m 1.5 B or 50 m 1.5 B 50 m B or 30 m 1.5 B or 50 m 1.5 B ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Which of the following structures are constructed parallel to shore line to develop a demarcating line between land area and water area? Sea walls, bulk heads and revetments Bulk heads, revetments and groynes Sea walls, bulk heads and groynes Sea walls, revetments and groynes Sea walls, bulk heads and revetments Bulk heads, revetments and groynes Sea walls, bulk heads and groynes Sea walls, revetments and groynes ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering The significant wave height is defined is the average height of the one – tenth highest waves one – third highest waves one – fifth highest waves one – fourth highest waves one – tenth highest waves one – third highest waves one – fifth highest waves one – fourth highest waves ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering By increasing the rise of lock-gates,(i) The length of the lock gate will increase(ii) Transverse stress due to water pressure on the gate will increase(iii) Compressive force on the gate will increase (i) and (ii) are correct Only (ii) is correct Only (iii) is correct (i) and (iii) are correct (i) and (ii) are correct Only (ii) is correct Only (iii) is correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP