Waste Water Engineering For efficient working of a sewer, it must be ensured that Neither (A) nor (B) A maximum velocity of 0.90 m/sec, is maintained at its maximum flow Both (A) and (B) Minimum velocity of 0.45 m/sec, is maintained at its minimum flow Neither (A) nor (B) A maximum velocity of 0.90 m/sec, is maintained at its maximum flow Both (A) and (B) Minimum velocity of 0.45 m/sec, is maintained at its minimum flow ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The sewer which resists sulphide corrosion, is Brick sewer Lead sewer Cast iron sewer R.C. sewer Brick sewer Lead sewer Cast iron sewer R.C. sewer ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The drop man holes are generally provided in sewers for Industrial areas Cities in plains Hilly town ships Large town ships Industrial areas Cities in plains Hilly town ships Large town ships ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The standard B.O.D. of water is taken for 5 days 1 day 2 days 3 days 5 days 1 day 2 days 3 days ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering ¾th or ¼th extra space is left in sewer pipes at maximum discharge for All listed here Low estimates of the average and maximum flows Unexpected increase in population Large scale infiltration of storm water All listed here Low estimates of the average and maximum flows Unexpected increase in population Large scale infiltration of storm water ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering If the diameter of sewer is 225 mm, the gradient required for generating self cleansing velocity, is None of these 1 in 120 1 in 100 1 in 60 None of these 1 in 120 1 in 100 1 in 60 ANSWER DOWNLOAD EXAMIANS APP