Building Construction For a rectangular foundation of width b, eccentricity of load should not exceed b/6 b/4 b/3 b/2 b/6 b/4 b/3 b/2 ANSWER DOWNLOAD EXAMIANS APP
Building Construction A pre-stressed concrete pile is Extremely durable All of these Easy to handle Lighter in weight Extremely durable All of these Easy to handle Lighter in weight ANSWER DOWNLOAD EXAMIANS APP
Building Construction During percussion drilling All listed here The soil to a considerable depth below the bottom of the hole gets disturbed Caving or mixing of strata are caused in soft soils or cohesion-less soils Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole All listed here The soil to a considerable depth below the bottom of the hole gets disturbed Caving or mixing of strata are caused in soft soils or cohesion-less soils Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole ANSWER DOWNLOAD EXAMIANS APP
Building Construction The rock formed from the solidification of molten matter (magma) is called: Metamorphic rock None of these Sedimentary rock Igneous rock Metamorphic rock None of these Sedimentary rock Igneous rock ANSWER DOWNLOAD EXAMIANS APP
Building Construction The triangular space formed between the extrados and the horizontal line drawn through the crown of an arch is known as Skewbacks Spandril Voussoirs Haunch Skewbacks Spandril Voussoirs Haunch ANSWER DOWNLOAD EXAMIANS APP
Building Construction To ensure that supporting area of an offset footing of a boundary wall is fully compressive, the C.G. of load must act At the centre of the base Neither (A), (B) nor (C) Within the middle third of the base Within the middle fifth of the base At the centre of the base Neither (A), (B) nor (C) Within the middle third of the base Within the middle fifth of the base ANSWER DOWNLOAD EXAMIANS APP