Find the number of strands of ACSR conductor for 3 layer transmission line?

 7
 29
 19
 1

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
If, for a given alternator in economic operation mode, the incremental cost is given by (0.012 P + 8) Rs/MWh, dPL/dP = 0.2 and plant λ = 25, then power generation is

 1250 MW
 750 MW
 1500 MW
 1000 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
What are the tests performed for oil-filled and gas-filled cables ?

 Load cycle tests.
 Thermal stability test.
 Impulse tests.
  All of these.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Demand factor of a plant is

 0
 less than 1
 1
 greater than 1

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Switchgear equipment include

  relays and CB.
  switches.
  fuses.
  all of these.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The load duration curve for a system is 8 hours 30 MW, 16 hours 25 MW and 24 hours 20 MW. The load factor will be

 0.25.
  0.83.
 1.3.
 0.44.

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Power Systems

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑