Power Systems Find the number of strands of ACSR conductor for 3 layer transmission line? 29 1 19 7 29 1 19 7 ANSWER DOWNLOAD EXAMIANS APP
Power Systems The steam power plant efficiency can be improved by decreasing the load on the plant. burning large amount of coal. using high temperature and high pressure steam. using large quantity of water. decreasing the load on the plant. burning large amount of coal. using high temperature and high pressure steam. using large quantity of water. ANSWER DOWNLOAD EXAMIANS APP
Power Systems What are the methods of laying underground cables? Draw - in - system / duct - pipe laying. Direct laying. None of these. Both A and B. Draw - in - system / duct - pipe laying. Direct laying. None of these. Both A and B. ANSWER DOWNLOAD EXAMIANS APP
Power Systems If the fault current is 2000 A, the relay setting is 50% and CT ratio is 400 : 5, then plug setting multiplier will be 15. 25. 10. 50. 15. 25. 10. 50. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In coal fired thermal power stations, what are the electrostatic precipitators used for? To remove dust particles setting on the bus bar conductors in the station switch yard All of these To keep the air heaters clean To collect the dust particles from the flue gases To remove dust particles setting on the bus bar conductors in the station switch yard All of these To keep the air heaters clean To collect the dust particles from the flue gases ANSWER DOWNLOAD EXAMIANS APP
Power Systems Mercury is choice with steam in binary vapor cycle because higher saturation temperature than other fluids. relative low vaporization pressure. higher critical temperature and pressure. all of above. higher saturation temperature than other fluids. relative low vaporization pressure. higher critical temperature and pressure. all of above. ANSWER DOWNLOAD EXAMIANS APP