RCC Structures Design A raft foundation is provided if its area exceeds the plan area of the building by 50 % 10 % 40 % 20 % 50 % 10 % 40 % 20 % ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design The system in which high tensile alloy steel bars (silica manganese steel) are used as pre-stressing tendons, is known as Magnel-Blaton system C.L. standard system Lee-McCall system Freyssinet system Magnel-Blaton system C.L. standard system Lee-McCall system Freyssinet system ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design In a cantilever retaining wall without a heel slab Thickness of the stem is kept same throughout All listed here Base slab is made 10 cm thicker than the stem Width of the base slab is kept 0.7 time the total height of the wall Thickness of the stem is kept same throughout All listed here Base slab is made 10 cm thicker than the stem Width of the base slab is kept 0.7 time the total height of the wall ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design Post tensioning system Is economical for large spans and is adopted now a days Was widely used in earlier days None of these Is not economical and hence not generally used Is economical for large spans and is adopted now a days Was widely used in earlier days None of these Is not economical and hence not generally used ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design A reinforced concrete cantilever beam is 3.6 m long, 25 cm wide and has its lever arm 40 cm. It carries a load of 1200 kg at its free end and vertical stirrups can carry 1800 kg. Assuming concrete to carry one-third of the diagonal tension and ignoring the weight of the beam, the number of shear stirrups required, is 40 35 30 45 40 35 30 45 ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design Columns may be made of plain concrete if their unsupported lengths do not exceed their least lateral dimension Four times Three times Five times Two times Four times Three times Five times Two times ANSWER DOWNLOAD EXAMIANS APP