Power Systems A 3-phase transmission line operating at Vs = 400 kV and has ABCD parameters A= D = 0.8∠0°, B = 100∠90° Ω, C = 0.5*10-6∠90° ℧. Find the no load receiving end voltage? 600 kV 500 kV 400 kV 320 kv 600 kV 500 kV 400 kV 320 kv ANSWER DOWNLOAD EXAMIANS APP
Power Systems For variable heads of near about but less than 30 meters, which type of turbine is used in hydro power station? Francis None of these Kaplan Pelton Francis None of these Kaplan Pelton ANSWER DOWNLOAD EXAMIANS APP
Power Systems In order to have lower cost of power generaion the load factor should be low but diversity factor should be high The load factor and diversity factor should be high the load factor and diversity factor should be low the load factor should be high but diversity factor should be low the load factor should be low but diversity factor should be high The load factor and diversity factor should be high the load factor and diversity factor should be low the load factor should be high but diversity factor should be low ANSWER DOWNLOAD EXAMIANS APP
Power Systems To improve the efficiency of thermal power plant ________________ is placed between boiler and turbine. air preheater. superheater. economizer. ash handling point. air preheater. superheater. economizer. ash handling point. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In hydroelectric power plants both operating and initial cost are high. operating cost is high and initial cost is low. operating cost is low and initial cost is high. both operating and initial cost are low. both operating and initial cost are high. operating cost is high and initial cost is low. operating cost is low and initial cost is high. both operating and initial cost are low. ANSWER DOWNLOAD EXAMIANS APP
Power Systems With reference to hydrometer station, the graphical representation of the discharge as function of time is known as Hectograph. Hydro-graph. Monograph. Load duration curve. Hectograph. Hydro-graph. Monograph. Load duration curve. ANSWER DOWNLOAD EXAMIANS APP