SSC JE Electrical 2019 with solution SET-2
While estimating domestic wiring cost, if the length of the PVC conduit required is 62 meters, then what is the length of the cable required?

186 meters
124 meters
100 meters
62 meters

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
Observe the figure and find the correct relation from the four given options?

i1 + i2 + i4 = i3 + i5 + i6
i1 + i2 + i3 = i4 + i5 + i6
i1 + i2 + i6 = i4 + i5 + i3
i4 + i2 + i3 = i1 + i5 + i6

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
Which of the following motors can be connected across a single-phase AC supply?

DC Series Motor
Differential compound motor
Cumulative compound motor
DC shunt motor

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
Both the main winding and auxiliary winding of a single-phase induction motor is placed on the ______?

Rotor
Stator
Neither stator nor rotor
Both stator and rotor

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
Which of the following lamps is used s a sign or an indicator lamp?

Halogen lamp
Fluorescent lamp
Incandescent lamp
Neon lamp

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP