Irrigation Engineering
Pick up the correct statement from the following and answer

In a level crossing, a cross regulator is provided on the canal below the crossing
In a level crossing, a crest with its top at the canal F.S.L. is provided across the drainage at its up-stream junction with canal
All of these
In a level crossing a regulator is provided across the drainage at its down-stream

ANSWER DOWNLOAD EXAMIANS APP

Irrigation Engineering
Pick up the correct sequence of the part of a canal system from the following

Head work-distributary-branch canal-minor
Head works-main canal-branch canal-distributary-minor
Heads works-branch canal-main canal distributary, minor
Head works-main canal-branch canal-minor-distributary

ANSWER DOWNLOAD EXAMIANS APP