Engineering Economics The sunk costs include: An invested capital that cannot be retrieved An unrecovered balance All of these A past expenditure An invested capital that cannot be retrieved An unrecovered balance All of these A past expenditure ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics The owner of the construction company makes use of the estimate: To assist in financial arrangements To determine economic feasibility of the project All of these To determine the capital investment costs To assist in financial arrangements To determine economic feasibility of the project All of these To determine the capital investment costs ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics A feasibility study shows that a fixed capital investment of P10,000,000 is required for a proposed construction firm and an estimated working capital of P2,000,000. Annual depreciation is estimated to be10% of the fixed capital investment. Determine the rate of return on the total investment if the annual profit is P3,500,000. 0.2833 0.3078 0.3012 0.2917 0.2833 0.3078 0.3012 0.2917 ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics What is another term for “unit method” for computing depletion? Percentage method Factor method Sinking fund method Initial cost method Percentage method Factor method Sinking fund method Initial cost method ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics Which one of the following is not a construction estimate? Conceptual preliminary budget None of these Definite estimate Initial feasibility estimate Conceptual preliminary budget None of these Definite estimate Initial feasibility estimate ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics Keeping in view, the feasibility order of magnitude, the preliminary, conceptual or budget estimates, are prepared by: Construction manager Owner himself/herself Architect/engineer Construction manager Construction manager Owner himself/herself Architect/engineer Construction manager ANSWER DOWNLOAD EXAMIANS APP