Irrigation Engineering
The rainfall on five successive days were measured as 100 mm, 80 mm, 60 mm, 40 mm and 20 mm respectively. If the infiltration index or the storm loss rate for the catchment area is earlier estimated as 50 mm/day, the total surface run off will be

140 mm
50 mm
90 mm
60 mm

ANSWER DOWNLOAD EXAMIANS APP

Irrigation Engineering
A counter berm is

A horizontal benching provided on the outside slope
A vertical benching provided on the inner edge of the bank
A horizontal benching provided on the inside slope
A vertical benching provided on the outer edge of the bank

ANSWER DOWNLOAD EXAMIANS APP