Concrete Technology and Design of Concrete Structures
Select the incorrect statement...

For heavy loads and large spans in buildings or bridges, post-tensioning system is cheaper than pretensioning system
The loss of prestress is more in pre-tensioning system than in post-tensioning system.
None of these
Pretensioning system has greater certainty about its durability.

ANSWER DOWNLOAD EXAMIANS APP

Concrete Technology and Design of Concrete Structures
The main reinforcement in the toe of a T- shaped R C. retaining wall is provided on i) top face parallel to the wall ii) top face perpendicular to the wall iii) bottom face paralleUo the wall iv) bottom face perpendicular to the wall The correct answer is

only (ii) is correct
(i) and (ii) are correct
(iii) and (iv) are correct
only (iv) is correct

ANSWER DOWNLOAD EXAMIANS APP

Concrete Technology and Design of Concrete Structures
Minimum pitch of transverse reinforcement in a column is

the least lateral dimension of the member
sixteen times the smallest diameter of longitudinal reinforcement bar to be tied
forty-eight times the diameter of transverse reinforcement
lesser of the above three values

ANSWER DOWNLOAD EXAMIANS APP