GETCO Exam Paper (30-11-2008) The number of pilot wires required for protecting 3-phase transmission lines using Translay System of protection is 6 3 2 4 6 3 2 4 ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) In the protection scheme relay functions as _____ device none of these sensing switching breaking none of these sensing switching breaking ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) An AC transmission line requires a VAR input: to increase power transmission to reduce losses to improve the regulation to improve stability to increase power transmission to reduce losses to improve the regulation to improve stability ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) When a star delta transformer bank of three single phase transformers is to be used for step down transformation with line voltages of 23000 V and 2300 V, the ratio of transformation will be 10.0:1 5.8:1 17.2:1 12.1:1 10.0:1 5.8:1 17.2:1 12.1:1 ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Corona usually occurs when the electrostatic stress in the air around the conductor succeeds 22 kV (maximum value)/cm 6.6 kV (rms value)/cm 30 kV (maximum value)/cm 11 kV (rms value)/cm 22 kV (maximum value)/cm 6.6 kV (rms value)/cm 30 kV (maximum value)/cm 11 kV (rms value)/cm ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Select the most suitable word from the given choices to fill in the blanks to make the sentence meaningfully completeIn the camps volunteers served one and all without _____ distinction discretion considertion discrimination distinction discretion considertion discrimination ANSWER DOWNLOAD EXAMIANS APP