GETCO Exam Paper (30-11-2008) If a combination of HRC fuse and a C.B. is employed, the C.B. operates for this combination is never employed in practice under all abnormal currents low over load currents short circuit currents this combination is never employed in practice under all abnormal currents low over load currents short circuit currents ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) In an overhead transmission line, wave traps are used for the detection of the _____ signals. carrier fault voltage fault power fault current carrier fault voltage fault power fault current ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The planning Commission was set up in January, 1948 September, 1947 March,1950 April, 1947 January, 1948 September, 1947 March,1950 April, 1947 ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Highest voltage for transmitting electrical power in India is (in 2008) 550 kV 400 kV 765 kV 700 kV 550 kV 400 kV 765 kV 700 kV ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The arc voltage in a C.B. is _____ with the arc current none of these lagging by 90˚ leading by 90˚ in phase none of these lagging by 90˚ leading by 90˚ in phase ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The power transmitted will be maximum when reactance is high sending end voltage is more corona losses are least receiving end voltage is more reactance is high sending end voltage is more corona losses are least receiving end voltage is more ANSWER DOWNLOAD EXAMIANS APP