DGVCL Exam Paper (11-12-2011)
The insulation coordination for UHV lines (above 500 kV) is done based on

Voltage level of the line
Lightning and switching surges
Lightning surges
Switching surges

ANSWER DOWNLOAD EXAMIANS APP

DGVCL Exam Paper (11-12-2011)
Which of the following correctly represents the sequence of operations of isolator, circiut breaker and earthing switch while opening a circuit?

Open isolator close circuit breaker-open earthing switch
Close earthing switch - open ciruit- breaker-open islotor
Close circuit breaker-close isolator - open earthing switch
Open circuit breaker-open isolator-close earthing switch