Industrial Engineering and Production Management ABC analysis deals with Controlling inventory costs money Flow of material Analysis of process chart Ordering schedule of job Controlling inventory costs money Flow of material Analysis of process chart Ordering schedule of job ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT has following time estimate Two time estimate Four time estimate Three time estimate One time estimate Two time estimate Four time estimate Three time estimate One time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good LS = LFD EF = ES + D All of these LF = LS + D LS = LFD EF = ES + D All of these LF = LS + D ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The basic difference between PERT and CPM is that PERT deals with events and CPM with activities Guessed times are used in PERT and evaluated times in CPM Costs are considered on CPM only and not in PERT Critical path is determined in PERT only PERT deals with events and CPM with activities Guessed times are used in PERT and evaluated times in CPM Costs are considered on CPM only and not in PERT Critical path is determined in PERT only ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive It represents a situation where extra resources are available and the completion of project is not delayed Any one of the above It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed Any one of the above It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project ANSWER DOWNLOAD EXAMIANS APP