If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later TRUE ANSWER : ? YOUR ANSWER : ?
The probability of completion of any activity within its expected time is 0.841 0.999 0.5 1 TRUE ANSWER : ? YOUR ANSWER : ?
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 2000 cum 500 cum 1500 cum TRUE ANSWER : ? YOUR ANSWER : ?
Interfering float is the difference between Total float and free float Free float and independent float None of these Total float and independent float TRUE ANSWER : ? YOUR ANSWER : ?
The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) Bar chart method TRUE ANSWER : ? YOUR ANSWER : ?
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % 1 More than 50 % 0.5 TRUE ANSWER : ? YOUR ANSWER : ?
Batching refers to Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch Controlling the quantity of each material into each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch TRUE ANSWER : ? YOUR ANSWER : ?
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 15 days 8 days 10 days TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct TRUE ANSWER : ? YOUR ANSWER : ?
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 3425 kg 4350 kg 2975 kg TRUE ANSWER : ? YOUR ANSWER : ?