The 'centre line method' is specially adopted for estimating Octagonal buildings Hexagonal buildings Circular buildings All of these TRUE ANSWER : ? YOUR ANSWER : ?
The brick work is measured in sq metre, in case of Half brick walls or the partition All of these Brick flat soling Honey comb brick work TRUE ANSWER : ? YOUR ANSWER : ?
If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is B + d + Sd B × d - Sd1/2 Bd + Sd2 ½ (Bd + Sd2) TRUE ANSWER : ? YOUR ANSWER : ?
The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 4.00 cum 3.00 cum 2.00 cum TRUE ANSWER : ? YOUR ANSWER : ?
The expected out turn of 12 mm plastering with cement mortar is 8.0 sq m 4.0 sq m 6.0 sq m 2.5 sq m TRUE ANSWER : ? YOUR ANSWER : ?
The expected out turn of 2.5 cm cement concrete floor per mansion per day 5.0 sqm 2.5 sqm 7.5 sqm 10 sqm TRUE ANSWER : ? YOUR ANSWER : ?
The order of booking dimensions is Breadth, length, height None of these Height, breadth, length Length, breadth, height TRUE ANSWER : ? YOUR ANSWER : ?
As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken All of these 1.20 liters for 15 users 1.80 liters for 5 to 10 users 1.35 for 20 users TRUE ANSWER : ? YOUR ANSWER : ?
The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3250 m³ 3225 m³ 3300 m³ TRUE ANSWER : ? YOUR ANSWER : ?
Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building All of these TRUE ANSWER : ? YOUR ANSWER : ?