Pick up the item whose weight is added to the weight of respective item, is All listed here Bolts Cleats Brackets TRUE ANSWER : ? YOUR ANSWER : ?
A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,500 m³ 26,000 m³ 27,500 m³ 27,000 m³ TRUE ANSWER : ? YOUR ANSWER : ?
The order of booking dimensions is Length, breadth, height None of these Breadth, length, height Height, breadth, length TRUE ANSWER : ? YOUR ANSWER : ?
In the mid-section formula The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections TRUE ANSWER : ? YOUR ANSWER : ?
If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by Prismoidal formula All of these Mid-section formula Trapezoidal formula TRUE ANSWER : ? YOUR ANSWER : ?
The brick work is measured in sq metre, in case of Half brick walls or the partition Honey comb brick work All of these Brick flat soling TRUE ANSWER : ? YOUR ANSWER : ?
If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is B × d - Sd1/2 Bd + Sd2 ½ (Bd + Sd2) B + d + Sd TRUE ANSWER : ? YOUR ANSWER : ?
The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3300 m³ 3225 m³ 3250 m³ 3275 m³ TRUE ANSWER : ? YOUR ANSWER : ?
Size, capacity and materials need be specified for Stop-cocks All of these Bib-cocks Ball valves TRUE ANSWER : ? YOUR ANSWER : ?
The rate of payment is made for 100 cu m (per % cu m) in case of Rock cutting Earth work in excavation All of these Excavation in trenches for foundation TRUE ANSWER : ? YOUR ANSWER : ?