Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants TRUE ANSWER : ? YOUR ANSWER : ?
Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than earliest event time of the following node TRUE ANSWER : ? YOUR ANSWER : ?
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be More than 50 % Less than 50 % 0.5 1 TRUE ANSWER : ? YOUR ANSWER : ?
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these TRUE ANSWER : ? YOUR ANSWER : ?
If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7 % and 15.9% 97.7% and 84.1% 15.9% and 97.7% 2.3% and 84.1% TRUE ANSWER : ? YOUR ANSWER : ?
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 25 15 20 TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct TRUE ANSWER : ? YOUR ANSWER : ?
Which one of the following represents an activity? All listed here Excavation for foundation Curing of concrete Setting of question paper TRUE ANSWER : ? YOUR ANSWER : ?
While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events Required time for each activity is established A project is divided into various activities All listed here TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct TRUE ANSWER : ? YOUR ANSWER : ?