If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same None of these expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A TRUE ANSWER : ? YOUR ANSWER : ?
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 3 1 2 TRUE ANSWER : ? YOUR ANSWER : ?
Updating may result in All of these Change of critical path Increase of project completion time Decrease of project completion time TRUE ANSWER : ? YOUR ANSWER : ?
The object of technical planning, is All listed here Preparation of estimates Preparation of specifications Initiating the procurement action of resources TRUE ANSWER : ? YOUR ANSWER : ?
Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity TRUE ANSWER : ? YOUR ANSWER : ?
The critical activity has Zero float Maximum float None of these Minimum float TRUE ANSWER : ? YOUR ANSWER : ?
Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct TRUE ANSWER : ? YOUR ANSWER : ?
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components TRUE ANSWER : ? YOUR ANSWER : ?
Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (ii) and (iv) are correct TRUE ANSWER : ? YOUR ANSWER : ?
During the construction period, price variation clause in contracts caters to Increase in rates of only important materials Rate of inflation Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element TRUE ANSWER : ? YOUR ANSWER : ?