The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 80 and 90 85 and 75 75 and 83 90 and 80 TRUE ANSWER : ? YOUR ANSWER : ?
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D All listed here LF = LS + D LS = LF - D TRUE ANSWER : ? YOUR ANSWER : ?
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of repetitive manufacture of a number of elements Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour Yes, because of heavier overheads and handling cost TRUE ANSWER : ? YOUR ANSWER : ?
The independent float affects only Succeeding activities Preceding activities The particular activity involved None of these TRUE ANSWER : ? YOUR ANSWER : ?
Railway projects are treated as Light construction Industrial construction None of these Heavy construction TRUE ANSWER : ? YOUR ANSWER : ?
Rolling resistance of a wheel depends upon<br/>(i) Vehicle load<br/>(ii) Grade<br/>(iii) Ground conditions (i) and (iii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct TRUE ANSWER : ? YOUR ANSWER : ?
Critical path lies along the activities having total float Negative Same Zero Positive TRUE ANSWER : ? YOUR ANSWER : ?
An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 31050 Rs. 37950 Rs. 50000 Rs. 34500 TRUE ANSWER : ? YOUR ANSWER : ?
Earliest finish of an activity is always Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node TRUE ANSWER : ? YOUR ANSWER : ?
The area under the Beta distribution curve is divided into two equal parts by Most likely time Optimistic time Expected time Pessimistic time TRUE ANSWER : ? YOUR ANSWER : ?