The main disadvantage of line organization, is Top level executions over work All listed here Extraordinary delay in communications Rigid structure TRUE ANSWER : ? YOUR ANSWER : ?
A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 5000 kg 12500 kg 22500 kg 10000 kg TRUE ANSWER : ? YOUR ANSWER : ?
A golden rule for the procurement of construction stones, suggests 67% at the site and 33% under procurement 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement TRUE ANSWER : ? YOUR ANSWER : ?
The time corresponding to minimum total project cost is Optimistic time Between normal time and crash time Crash time Normal time TRUE ANSWER : ? YOUR ANSWER : ?
Which of the following excavators is most suitable for digging under water? Clam shell Hoe Dipper shovel Drag line TRUE ANSWER : ? YOUR ANSWER : ?
CPM is All listed here Is built of activities oriented programme Synthesising in concepts Is based on time estimate TRUE ANSWER : ? YOUR ANSWER : ?
A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 6960 Rs. 1740 Rs. 5220 Rs. 3480 TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 TRUE ANSWER : ? YOUR ANSWER : ?
PERT analysis is based on Pessimistic time Most likely time All listed here Optimistic time TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 TRUE ANSWER : ? YOUR ANSWER : ?