If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 15.9% and 97.7% 2.3% and 84.1% 97.7% and 84.1% 97.7 % and 15.9% TRUE ANSWER : ? YOUR ANSWER : ?
Economic saving of time results by crashing Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity TRUE ANSWER : ? YOUR ANSWER : ?
Railway projects are treated as Light construction None of these Heavy construction Industrial construction TRUE ANSWER : ? YOUR ANSWER : ?
Sensitivity analysis is a study of Economics of cost and benefits of the project Change in output due to change in input Comparison of profit and loss Comparison of assets and liabilities TRUE ANSWER : ? YOUR ANSWER : ?
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Shortest duration Least cost slope Highest cost slope Longest duration TRUE ANSWER : ? YOUR ANSWER : ?
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Concrete Ice Loose sand Earth TRUE ANSWER : ? YOUR ANSWER : ?
Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero TRUE ANSWER : ? YOUR ANSWER : ?
The most popular type of organization used for Civil Engineering Constructions, is Line organization Functional organization Line and staff organization Effective organization TRUE ANSWER : ? YOUR ANSWER : ?
Various activities of a project, are shown on bar charts by Crosses Vertical lines Horizontal lines Dots TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct TRUE ANSWER : ? YOUR ANSWER : ?