The area under the Beta distribution curve is divided into two equal parts by Optimistic time Pessimistic time Expected time Most likely time TRUE ANSWER : ? YOUR ANSWER : ?
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 15 days 9 days 10 days TRUE ANSWER : ? YOUR ANSWER : ?
Slack time refers to An event None of these An activity Both event and activity TRUE ANSWER : ? YOUR ANSWER : ?
The process of incorporating changes and rescheduling or replanning is called Critical path scheduling Resource levelling Updating Resource smoothening TRUE ANSWER : ? YOUR ANSWER : ?
The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct TRUE ANSWER : ? YOUR ANSWER : ?
A CPM family includes CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) All listed here CPP (Critical Path Plotted) TRUE ANSWER : ? YOUR ANSWER : ?
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 3tm+ tp/3 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 4tm+ tp/4 TRUE ANSWER : ? YOUR ANSWER : ?
Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct TRUE ANSWER : ? YOUR ANSWER : ?
Time and progress chart of a construction, is also known as Gantt chart All listed here Modified Mile stone chart Bar chart TRUE ANSWER : ? YOUR ANSWER : ?
The time with which direct cost does not reduce with the increase in time is known as Optimistic time Normal time Standard time Crash time TRUE ANSWER : ? YOUR ANSWER : ?