Preliminary project report for a road project must contain The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 TRUE ANSWER : ? YOUR ANSWER : ?
A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 7.87 years 3.7 years 5 years 4.23 years TRUE ANSWER : ? YOUR ANSWER : ?
Free float is mainly used to Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Establish priorities Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following statements for a power shovel:<br/>(i) Output can be increased by reducing the angle of swing for a given depth of cut.<br/>(ii) For a given angle of swing, output will be maximum at optimum depth of cut.<br/>(iii) Output can be increased by keeping the depth of cut less than optimum depth.<br/>(iv) Output can be increased by increasing the size of shovel. (i) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct TRUE ANSWER : ? YOUR ANSWER : ?
Critical path lies along the activities having total float Same Positive Negative Zero TRUE ANSWER : ? YOUR ANSWER : ?
PERT technique of network analysis is mainly useful for Research and development projects Large and complex projects Deterministic activities Small projects TRUE ANSWER : ? YOUR ANSWER : ?
In resources levelling Total duration of project is reduced Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased TRUE ANSWER : ? YOUR ANSWER : ?
The time with which direct cost does not reduce with the increase in time is known as Crash time Normal time Standard time Optimistic time TRUE ANSWER : ? YOUR ANSWER : ?
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 20 kg/tonne 9 kg/tonne 6 kg/tonne 2 kg/tonne TRUE ANSWER : ? YOUR ANSWER : ?