Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities TRUE ANSWER : ? YOUR ANSWER : ?
The most suitable type of equipment for compaction of cohesive soils is Vibratory rollers Tampers Sheep foot rollers Smooth-wheeled rollers TRUE ANSWER : ? YOUR ANSWER : ?
Which of the following earth moving machines has the shortest cycle time? Clam shell Hoe Dipper shovel Drag line TRUE ANSWER : ? YOUR ANSWER : ?
Total float for any activity is defined as the difference between Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity TRUE ANSWER : ? YOUR ANSWER : ?
Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct TRUE ANSWER : ? YOUR ANSWER : ?
For the network shown in the given figure, the expected time for the activity All listed here 1-2 is 4 3-4 is 8 2-3 is 7 TRUE ANSWER : ? YOUR ANSWER : ?
The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct TRUE ANSWER : ? YOUR ANSWER : ?
For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Good common earth Moist loam Wet sticky clay Well blasted rock TRUE ANSWER : ? YOUR ANSWER : ?
Works costing less than Rs. 20,000 are treated as Minor projects Any project All listed here Major projects TRUE ANSWER : ? YOUR ANSWER : ?
While filling the tender for any work, the contractor considers Availability of labour Availability of construction materials Site survey All listed here TRUE ANSWER : ? YOUR ANSWER : ?