The main disadvantage of line organization, is Extraordinary delay in communications All listed here Top level executions over work Rigid structure TRUE ANSWER : ? YOUR ANSWER : ?
For the network shown in the given figure, the expected time for the activity 2-3 is 7 1-2 is 4 3-4 is 8 All listed here TRUE ANSWER : ? YOUR ANSWER : ?
The critical activity has Minimum float Zero float Maximum float None of these TRUE ANSWER : ? YOUR ANSWER : ?
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Constraint Free float Dummy TRUE ANSWER : ? YOUR ANSWER : ?
Updating may result in Change of critical path Decrease of project completion time All of these Increase of project completion time TRUE ANSWER : ? YOUR ANSWER : ?
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Total float Duration Interfering float Free float TRUE ANSWER : ? YOUR ANSWER : ?
Economic saving of time results by crashing Cheapest noncritical activity Cheapest critical activity Costliest critical activity Costliest noncritical activity TRUE ANSWER : ? YOUR ANSWER : ?
The direct cost of a project with respect to normal time is Zero Infinite Maximum Minimum TRUE ANSWER : ? YOUR ANSWER : ?
Completion of an activity on CPM network diagram, is generally known Event All listed here Connector Node TRUE ANSWER : ? YOUR ANSWER : ?