Which one of the following represents an event? Plastering of walls Fixing of door Selecting sites Concrete cured TRUE ANSWER : ? YOUR ANSWER : ?
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 2000 cum 1000 cum 1500 cum TRUE ANSWER : ? YOUR ANSWER : ?
Which one of the following is not an excavating and moving type of equipment? Dump truck Clam shell Scraper Bulldozer TRUE ANSWER : ? YOUR ANSWER : ?
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 2 3 1 TRUE ANSWER : ? YOUR ANSWER : ?
Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities TRUE ANSWER : ? YOUR ANSWER : ?
Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct TRUE ANSWER : ? YOUR ANSWER : ?
For a given size of bucket, the ideal output of a dragline will be least in Wet sticky clay Moist loam Good common earth Sand and gravel TRUE ANSWER : ? YOUR ANSWER : ?
Time and progress chart of a construction, is also known as All listed here Modified Mile stone chart Gantt chart Bar chart TRUE ANSWER : ? YOUR ANSWER : ?
Power stations are generally treated as Industrial construction Light construction Heavy construction Electrical construction TRUE ANSWER : ? YOUR ANSWER : ?
Final technical authority of a project lies with Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer TRUE ANSWER : ? YOUR ANSWER : ?