Sinking fund is The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following statements:In the bar chart planning<br/>1. Interdependence of the operations cannot be portrayed.<br/>2. Progress of work can be measured.<br/>3. Spare time of the activities can be determined.<br/>4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct TRUE ANSWER : ? YOUR ANSWER : ?
In resources levelling Total duration of project is increased Total duration of project is reduced Uniform demand of resources is achieved Cost of project is controlled TRUE ANSWER : ? YOUR ANSWER : ?
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 6 kg/tonne 9 kg/tonne 2 kg/tonne 20 kg/tonne TRUE ANSWER : ? YOUR ANSWER : ?
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/6 to + 4tm+ tp/5 to + 3tm+ tp/3 to + 4tm+ tp/4 TRUE ANSWER : ? YOUR ANSWER : ?
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct TRUE ANSWER : ? YOUR ANSWER : ?
The reduction in project time normally results in Decreasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both TRUE ANSWER : ? YOUR ANSWER : ?
The technique for establishing and maintaining priorities among the various jobs of a project, is known Slotting technique for scheduling Event flow scheduling technique Short interval scheduling Critical ratio scheduling TRUE ANSWER : ? YOUR ANSWER : ?
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Free float Event Dummy TRUE ANSWER : ? YOUR ANSWER : ?