A CPM family includes All listed here MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) CPA (Critical Path Analysis) TRUE ANSWER : ? YOUR ANSWER : ?
Time and progress chart of a construction, is also known as All listed here Modified Mile stone chart Gantt chart Bar chart TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 TRUE ANSWER : ? YOUR ANSWER : ?
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these TRUE ANSWER : ? YOUR ANSWER : ?
While filling the tender for any work, the contractor considers Site survey All listed here Availability of labour Availability of construction materials TRUE ANSWER : ? YOUR ANSWER : ?
Final technical authority of a project lies with Assistant Engineer Executive Engineer Chief Engineer Superintending Engineer TRUE ANSWER : ? YOUR ANSWER : ?
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 8,50,000 Rs. 6,50,000 Rs. 4,75,000 Rs. 5,75,000 TRUE ANSWER : ? YOUR ANSWER : ?
For the execution of a project, a contractor is A firm An agency A person All listed here TRUE ANSWER : ? YOUR ANSWER : ?
Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 TRUE ANSWER : ? YOUR ANSWER : ?
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 6 kg/tonne 2 kg/tonne 9 kg/tonne 20 kg/tonne TRUE ANSWER : ? YOUR ANSWER : ?