Engineering Economics Pick up the correct method adopted for developing the approximate or conceptual estimates from the following: Cost per function method Cost per square metre Base unit method All of these Cost per function method Cost per square metre Base unit method All of these ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics The construction estimate of a project is used by: All of these The consulting architect/engineer The contractor of the project The owner of the facility All of these The consulting architect/engineer The contractor of the project The owner of the facility ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand? 1.6 hours per unit 1.2 hours per unit 1.0 hour per unit 1.4 hours per unit 1.6 hours per unit 1.2 hours per unit 1.0 hour per unit 1.4 hours per unit ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics The unrecovered depreciation which results due to poor estimates as to the life of the equipment is called ______. Annuity In-place value Economic life Sunk cost Annuity In-place value Economic life Sunk cost ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics What is the type of annuity where the first payment does not begin until some later date in the cash flow? Perpetuity Ordinary annuity Annuity due Deferred annuity Perpetuity Ordinary annuity Annuity due Deferred annuity ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics What refers to a document that shows proof of legal ownership of a financial security? Bond Bank note Check Coupon Bond Bank note Check Coupon ANSWER DOWNLOAD EXAMIANS APP